Terex Dungannon, Structural Enhancements to Crane Rail

The Project delivered construction works for the Structural Enhancements to the existing crane rails in Hall J to support the installation (by others) of two new cranes for Terex operational needs.

Key Features:

  • Breaking out of existing concrete floor slab, installation of pad foundations and reinstatement of the floor
  • Installation of additional supporting structural steel columns to the existing crane rail and structural support bridging elements
  • Remove existing crane rail guide track and install new guide
  • Remove existing roller shutter door and reinstate with blockwork and cladding
  • Works were undertaken outside of Terex normal working hours

 

Key Project Information
Architect Albert Fry Associates
Value 110 K
Duration 6 Weeks
Extra Information
Location Dungannon, Co Tyrone
Sectors Commercial